Dec 23
Blocks for the foundation have all been laid. This is the view from what will become the front porch.
Dec 21
They are laying the blocks for the foundation.
Dec 16
Blocks for the foundation have been delivered.
Dec 10
Footings have been poured
Dec 9
Driveway has been cleared and bricks have been dropped off (albeit a little early)
Dec 3
Looking to the street from where the house will be
Footings have been dug
Nov 14
Clearing the land has commenced. Look at the size of some of the trees